Owners & Construction Management
Challenges and options regarding management of Construction.
Earl Worsham
In the litigated Construction world of today building
Owners and Corporate Executives are faced with many
challenges and options regarding management of Construction
projects. However; with a basic understanding of several of
the options Owner's & Executives can select what is best
for their project, achieve a level of protection and most
importantly assurance of a successful project. Another item
that needs to be understood is a construction project is
not a painless undertaking; all projects create
disruptions, inconveniences, and pulls key personnel away
from their normal duties. Not to mention dealing with
utility interruptions, design issues requiring correction,
project decisions to make (where, when, & how) and
resolving Contractor issues. The Architect and Engineer
must also be monitored and managed to insure
clarifications, design issues are being resolved in a
timely manner, along with insuring full compliance of all
contractual obligations.
From project conception, internal meetings, project design,
and through completion of the last punch list item an Owner
or Executive needs complete written documentation kept in
an organized manner for the project. On large projects with
long durations good project documentation is very crucial
as anyone involved in the project could have personnel
changes prior to the completion date. Another key item is
the project must be kept moving forward at all costs as an
Owner cannot allow or afford to have the project to sit
idle because of delayed Owner decisions or awaiting design
correction of design issues. Even if an Owner change needs
to be implemented immediately but would impact the critical
path of the project schedule it may be less costly to
implement the change at a later date even though the change
would require some demolition of installed work.
Now we are back to the options an Owner or Executive have
regarding how to manage a construction project.
Negotiated Projects - Run smoother and have less
issues to deal with but one of the more costly routes (15%
to 30% more than a bid project). Negotiated Projects are only
second to Design build in Contractor preference of
performing work. The additional cost is due to the
Contractor's reputation at risk and will utilize top
Sub-Contractors on the project (generally does not bid to
more than two Subs in each trade). The Contractor is also
assured of a guaranteed profit margin of 11% to 15% (in
this market area) which is in most cases at least double of
his bid margins. However, this type of project the
Contractor must justify its cost to the Owner and can only
bill the final cost of completion amount.
Bid Project - Tend to be the less costly approach but
require a tremendous more amount of time to manage as
Contractors will push issues to their limits and request
clarifications on minor details. Contractors also open the
bidding to most Sub-Contractors and will utilize the lowest
numbers to win the bid award. Contractors will bid this
type of a project as low as a 3% profit margin and will
beat down Sub-Contractor whom will have numerous exclusions
attached to the bids. This is where the problems begin as
Contractors will only look at the numbers on bid day then
realize the exposure. On the first day the Contractor will
begin submitting design alternatives and recommend
substitute materials to reduce project costs. The next
thing that occurs is design deficiencies will not be
submitted by the Contractor until the time of critical path
impact with a delay claim included in the change order.
At Risk Construction Management - This seems to be the
Construction raze at this time and many of the large
General Contracting firms are offering this service. At
Risk Construction Management means the Owner is assured the
project will not exceed the estimated cost and if so is
picked up by the Contractor or Construction Management
Firm, should any monies be left over these are returned to
the Owner excluding any bonuses that may be included.
Utilizing a Contractor for this type of service does not
offer any Owner protection or provides Owner documentation
of the project. Generally what occurs is Contract's have a
bid rate and a sale rate for their labor and will submit
the cost of the sale rate labor on pay applications to
reach the estimated cost of the project so there is not any
project savings to the Owner. At Risk Construction
Management firms will document a project for the Owner,
however will also be limiting their exposure should the
project develop major issues.
Construction Management Firms - Offer the Owner the
highest level of protection and planning on a Construction
project along with having the most accurate documentation
of the project because when contracted they are an
extension of the Owner as a Professional Consultant. CM
Firms are also dependent on their reputation and will
manage a project in the best interest of the Owner because
they are not at risk financially and do not have a vested
interest in the project due to set fees and / or hourly
rates. CM Firms will keep the Owner informed of all project
issues and assist the Owner with determining the best
resolution. CM Firms will be out ahead of the Contractor
clearing the path for subsequent installations and
evaluating for potential issues that could arise. The
Contract Documents are also implemented to the fullest
extent along with insuring Contractual obligations are met
by all partied including A&E Firms. CM Firms also offer the
highest level of Owner protection should a litigation issue
arise.
The above information is an outline or guide to assist
Owners and Corporate Executives to determine what is the
best method for their organization to manage a construction
project.
|